Phone: (660) 646-3553 Email: JGarrison@Irvinbilt.com
|
|
Typically Irvinbilt Constructors, Inc. has from four to six projects in various stages of completion underway at any one time. We invite you to view our slate of current projects on this page.
Project: Little Otter Creek Reservoir Structures Owner: Caldwell County Commission Location: Caldwell County, Missouri Engineers: USDA Natural Resources Conservation Service (NRCS) and Allstate Consultants LLC Contract Amount: $2,069,588 Scheduled Completion Date: October 2024 Superintendent: Bill Meyers
After over two decades of planning, design, reviews, and permitting, construction of the Little Otter Creek Reservoir is underway. An earthen dam will be constructed forming a 344-acre reservoir that will provide water security, flood damage reduction, and water-based recreation for the region. Under multiple prime contracts, Phillips Hardy, Incorporated of Boonville, Missouri is constructing the reservoir and Irvinbilt Constructors, Inc. is building the concrete control structures and installing the piping.
The reservoir, located about three miles east of Hamilton on the South side of US Highway 36, will supply 1.24 million gallons of drinking water per day to the county and surrounding areas, reduce flooding along Little Otter Creek, and provide recreation for area residents and visitors.
|
Project: Cameron Pipeline, BP Pump Station, and Storage Tank Owner: Northwest Wholesale Water Commission Location: St. Joseph, Missouri Engineers: Bartlett & West, Inc. and CDM Smith Contract Amount: $3,247,300 Scheduled Completion Date: December 2023 Superintendent: Steve Case
This project will supply water to several area communities. Construction of a pipeline serving Cameron, Maysville, and Stewartsville, had long been a dream of the Great Northwest Wholesale Water Commission. The project consists of a package pump station, a 450,000-gallon ground storage water tank, a centralized 300,000-gallon elevated water storage tank, and a 36-mile pipeline, under three separate contracts. Irvinbilt Constructors was awarded the contract for construction of the pump station and ground storage tank. BRB Contractors, Inc. will install the pipeline, and Caldwell Tanks, Inc. will provide the elevated storage tank.
The pipeline will run parallel with U.S. Highway 36 and Missouri Highway 33. With Missouri American Water Company, we are constructing the ground storage tank and pump station on a site on the east side of St. Joseph. The pipeline will extend to an elevated tank east of Stewartsville. From there, a line will run to Cameron, and another portion will be installed north along Highway 33 to Maysville. All three cities will receive domestic water as a result of the project.
In addition to constructing the concrete ground storage tank and pump station, Irvinbilt is providing the site grading, crushed rock paving, chain-link fencing, interconnecting piping, instrumentation, and electric work at the St. Joseph site.
|
Project: Southwest Wastewater Treatment Plant and Primary Treatment Rehabilitation Owner: City of Springfield Location: Springfield, Missouri Engineer: Burns & McDonnell Contract Amount: $3,682,640 Scheduled Completion Date: February 15, 2024 Superintendent: Brad Zahner
Springfield’s Southwest Wastewater Treatment Plant, constructed in 1959, sends 35 million gallons of sewage flow to Wilson Creek each day. The city council realizing that the existing equipment is corroded, outdated, and past its useful life, and wanting to make sure they are following state and federal regulations and are taking care of Wilson’s Creek, moved forward with a plan to rehabilitate of part of the plant. This project will provide an additional pump that will increase the plant’s capacity for incoming water from 75 million gallons per day to 100 million gallons per day.
This added capacity will reduce the risk of the plant being non-compliant with state or federal regulations during heavy rain events when storm water flows are high. Also, more than thirty old corroded aluminum gates used to control sewage as it moves through the plant, directing flow to different basins, will be replaced. The new gates will be made of stainless steel and will have automatic actuators that allow the gates to be controlled remotely from the control room.
Additional work involves replacing conduit, wiring, weirs and mixers in sewage basins. The project will also add oxygen sensors that detect how much oxygen is present in the sewage and automatically control the aeration.
|
Project: Moberly Correctional Center Wastewater Treatment Plant Improvements Owner: State of Missouri Location: Moberly, Missouri Engineer: Bartlett & West, Inc. Contract Amount: $3,817,750 Scheduled Completion Date: October 15, 2023 Superintendent: Casey Jaynes
Work is underway by Irvinbilt Constructors to make needed improvements to the existing Moberly Correctional Center Wastewater Treatment Plant located south of Moberly, Missouri. The project consists of providing and installing a headworks building, lift station, flow control structure, Triplepoint NitrOx tank and equipment, blowers for lagoon aeration, UV disinfection equipment, flow metering, interconnecting piping, instrumentation, and electrical equipment.
|
|
|
Customer Testimonials
We have performed over forty subcontracts for Irvinbilt Constructors and Irvinbilt Company earlier. We first started with Irvinbilt in 1998 when Don Garrison was running the water, wastewater, and pool division of the company. From day one they have been the best general contractor for whom we have worked. When Joe Garrison took over it was a seamless transition and we've experienced all the same positive benefits in working with Irvinbilt since we started work for them twenty-four years ago.
--Tom Nelson, President, Missouri Electric, Inc
|
|
|